We are thrilled to announce the starting of PQT’s for automatic welding works on the MGS-III pipeline project by Larsen & Toubro in KSA. Larsen & Toubro will utilize two complete welding spreads with our Qapqa PWT auto XCS welding stations for the mainline welding works.
One spread of 6 Qapqa Auto XCS welding stations are to be delivered within this month.

Project specifications:
- Client: Saudi Aramco
- Contractor: Larsen & Toubro Energy Hydrocarbon
- Project: (MGS-3) Master Gas System Network Saudi Arabia | Package # 08 | East - West Gas pipeline EWPS-8 To EWPS-10
- Location: KSA
- Pipe diameters: 56”
- Medium: Natural gas
- Length: 480 km
- WT: 14.26 | 17.65 | 20.26mm

Qapqa PQT MGS-III pipeline